Calculate hole volume (cylinder)
Hole Volume = π × r² × Depth r = half the diameter; a 10″ diameter × 3 ft deep hole = π × (5/12)² × 3 = 1.636 ft³
Calculate gravel base volume
Gravel Volume = π × r² × Gravel Depth Subtract from total hole to get concrete zone; 6″ gravel base in 10″ hole = 0.273 ft³
Subtract post displacement
Post Displacement = Post Width² × (Depth − Gravel Depth) A 4×4 post (3.5″ actual = 0.292 ft side) displaces 0.292² × 2.5 ft ≈ 0.213 ft³ of concrete space; using nominal for conservative estimate
Calculate concrete volume per hole
Concrete = Hole Volume − Gravel Volume − Post Displacement Apply waste factor: Concrete × (1 + Waste%); example: 1.636 − 0.273 − 0.213 = 1.15 ft³ net, with 10% = 1.27 ft³
Calculate bags required
Bags per Hole = ⌈Concrete per Hole ÷ Yield per Bag⌉ 80 lb bag = 0.60 ft³ → 1.27 ÷ 0.60 = 2.11 → 3 bags per hole; total = bags per hole × number of holes
Frequently Asked Questions
As a rule of thumb, most 8-ft fence posts with a 4×4 in a 10″ × 3 ft hole need 2–3 bags of 80 lb concrete.
Bury 1/3 of the total post length. An 8-ft post needs at least 2.5 ft below grade. Add 6 inches below the frost line in cold climates.
At minimum 3× the post width. A 4×4 post needs a 12″ hole; a 6×6 post needs an 18″ hole. Go wider in sandy or loose soil.
Yes — 4–6 inches of crushed gravel improves drainage and significantly extends post life by preventing standing water at the base.
10″ × 2.5 ft deep: 1–2 bags of 80 lb. 10″ × 3 ft deep: 2–3 bags. 12″ × 3.5 ft: 3–4 bags.
Fast-setting concrete (Quikrete Fast-Setting) can be poured dry and sets in 20–40 minutes. Standard mix also works well and is slightly less expensive.
Fast-setting mix: 20–40 minutes. Standard mix: 24–48 hours before attaching fence panels. Cold weather slows the cure significantly.
It varies by location. Zone 6: 18–24″, Zone 5: 30–36″, Zone 4: 36–48″. Always check local building code — footings must extend below the frost line.